Budget

Budget and what-if decisions

Main Level Remodel - Generic demo project data

Upload receipt
Original budget$125,000
Approved budget$132,400
Actual spent$48,920
Projected final$139,850
Variance+$14,850
Contingency left$6,100
What-if decision

Flooring material

$0 impact
Projected final$139,850
Contingency left$6,100

Choosing LVP moves the project by $0 compared with the current LVP allowance.

Budget categories

Estimated, quoted, approved, actual, and variance

Every major variance links back to a document or decision.

CategoryEstimatedQuotedApprovedActualVarianceStatusReference
Demo$3,500$3,500$3,500$3,500$0paidProject record
Framing$4,200$4,200$4,200$2,100$0in progressProject record
Electrical$6,000$6,800TBDTBD+$800needs reviewElectrical contractor
Plumbing$4,500$4,250$4,250$2,100-$250approvedProject record
HVAC$5,800$5,800$5,800$1,400$0in progressProject record
Drywall$4,900$4,900$4,900$4,900$0paidProject record
Flooring$4,200$8,900TBDTBD+$4,700decision pendingFlooring material
Cabinets$14,200$18,400TBDTBD+$4,200over allowanceCabinet upgrade
Countertops$4,800$4,800$4,800TBD$0approvedProject record
Paint$3,200$3,200$3,200TBD$0approvedProject record
Fixtures$3,800$4,100TBDTBD+$300quote receivedProject record
Deck$9,800$11,200$9,800$4,200+$1,400approvedDeck railing change
Permits$1,200$1,200$1,200$600$0partialProject record
Miscellaneous$4,900$4,900$4,900$1,620$0in progressProject record